Floods, Fires and Failed Transformers: 31 Incidents That Hit India's Renewable Plants Since 2023

Physical incidents at single plants rarely make the news. Floods are the most common, five plants were hit more than once, and insurance often pays only part of the loss, late.

Wattscape Insights · 19 Nov 2026 · Figures as of 8 Nov 2026

Key points
  • Wattscape recorded 31 physical incidents at 30 Indian renewable project companies since 2023: 16 floods or heavy rain, 8 equipment failures, 4 fires and 3 cyclones.
  • Five plants were hit twice or more, including a solar plant flooded in December 2023 and again in December 2024.
  • Insurance helps but rarely makes a plant whole: one wind farm recovered Rs 20.02 crore against Rs 25.50 crore of cyclone repairs, and a 1,200 MW hydro plant has received about Rs 250 crore against a Rs 5,084 crore claim.

The week's signal: two cyclones and a transformer

In the first week of November, Andhra Pradesh reported more than Rs 500 crore of damage to its power network from Cyclones Arnab and Murasu. The same week, a 300 MW solar plant in Gujarat had its credit rating upgraded; it is a plant whose first months of operation had been hit by a transformer failure: its output from February to September 2026 was 13.2% DC PLF against a P90 estimate of 19.02%, before the transformer was replaced and generation recovered.

Incidents like these rarely reach the news when they happen at a single plant. Wattscape records them on each project company's page, so we went back through every flood, cyclone, fire, equipment failure and insurance claim recorded since 2023, checked each by hand, and counted each incident once per plant.

Floods are the most common, and not only for hydro

Of the 31 incidents, 16 were floods or heavy rain, 8 were equipment failures, 4 were fires and 3 were cyclones. Hydro plants in the Himalaya took the heaviest blows, with the 2023 monsoon shutting at least six plants in Himachal Pradesh, Uttarakhand and Sikkim. But nine of the floods were at solar plants, in Tamil Nadu, Uttar Pradesh, Karnataka and Maharashtra.

Location matters more than technology. A solar plant in Uttar Pradesh that sits next to a seasonal water body flooded in 2023 and again in June 2025. A solar plant in Tamil Nadu was flooded by Cyclone Michaung in December 2023, before it was commissioned, and again by a flash flood in December 2024; its first full year's output was well below P90.

Physical incidents at renewable plants since 2023, by cause (incidents)
0.04.69.213.818.416Flood or heavy rain8Equipment failure4Fire3Cyclone

Source: Wattscape analysis

Equipment failures cost months, not days

Transformer failures stand out. Besides the Gujarat solar plant, a wind farm in Kutch lost output to a transformer failure in June and July 2025, and its PLF fell to 28.46% in ten months of FY26 against 37.08% in FY24. An earlier transformer failure at a Rajasthan wind site took almost a year to repair. Blade damage hit wind turbines in Karnataka, Kutch and Maharashtra, and inverter faults started fires at two solar plants in one portfolio in 2024, idling 12.5% of one plant's capacity for four months.

Wind farms in Kutch carry a combined exposure: Cyclone Biparjoy in June 2023 hit 17 of 51 turbines at one farm, and the same district has seen transformer failures, blade damage and fires since.

Physical incidents since 2023, by technology (incidents)
0.03.77.511.214.913Solar8Wind7Hydro2Wind-solar hybrid1Rooftop solar

Source: Wattscape analysis

Insurance pays, but partly and late

Where insurance figures are on record, they show what it is worth in practice. The Kutch wind farm hit by Biparjoy received Rs 20.02 crore in September 2024, fifteen months after the cyclone, against repairs of Rs 25.50 crore. A 20 MW solar plant flooded in 2024 received about Rs 7 crore across two financial years. A solar plant in Karnataka that lost 11 MW to floods in mid-2024 had the capacity back only in April 2026, funded from its own cash and insurance. At the extreme, a 1,200 MW Himalayan hydro plant shut by a flash flood in October 2023 has filed a claim of Rs 5,084 crore and had received about Rs 250 crore by August 2025.

Several portfolios bridged the gap with reserves: one solar pool met its restoration costs from insurance, an equipment maintenance reserve and surplus cash.

What lenders and investors should ask

Four questions follow from the record. Is the site in a flood path or next to a water body, and what drainage and module heights were designed for? Are critical spares, especially transformers, on hand or on a short lead time? Does the insurance cover business interruption as well as physical damage, and what is the operator's claims history? And are there reserves, such as a maintenance reserve or debt service reserve, sized to carry the plant through a months-long outage?

None of this is visible in a portfolio's headline capacity. It is visible plant by plant, on each company's record.

Method. Every flood, heavy rain, cyclone, storm, fire, equipment failure and insurance claim recorded for the project companies Wattscape tracks, confirmed by hand. Incidents from 2023 to November 2026; one count per incident per plant, even where several companies share the plant. Wattscape analysis.